Heavy Industry » PROJECTS IN GREECE » MANUFACTURING MAINTENANCE PROJECTS » MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX

Description

MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX

Project

:

Maintenance works at the Flexicoker unit during S.D. of March 2014 in the Elefsina Industrial Complex

Owner

:

Hellenic Petroleum S.A.

Contract

:

4403018417

Duration

:

34 days

Budget

:

718.886

Brief Description

:

The project included the following main activities:

 

A.  Replacing plate of 11.00met by 2.89metr with thickness 28mm , Grade 70 at the Bulge Area of Gasifier (32-R-003) following all the necessary NDT’S.

 

B. Maintenance work on equipment unit of FLEXICOKER (U-32)

·         Unit and equipment blinding and de-blinding after the end of works.

·         Opening of equipment for internal and external inspection: Reactors, Vessels ,Heaters and transfer lines and final restoration.

·         Internal repairs resulting from the inspection in Reactors 32-R-001, 32-R-002(Heater),32-R-003(Gasifier) and transfer lines: modification of snouts in  Reactor 32-R-001/C001 , replacement of nozzles in 32-R-002 ,installation of  supports in 32-R-002,installation of new supports in to 32-R-001 ,repair in transfer lines.

C. Installation of two new nozzles in Reactor 32-R-001 following all the   necessary NDT’S.

 

D. Piping  work

  • Piping works in unit maintenance on pipes diameter ½’’ ÷ 16’’ ,C.S. material ,alloy steel, stainless steel.
  • Hydraulic tests of piping networks: 5 ÷ 135 bar.

 

E.    Replacement of valves of all types from 1’’ ÷ 28’’.Total items: 170.

 

Hellenic Petroleum SA provided all the project's key materials to the Contractor except from the materials for steel structures.

 

 

MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX
MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX MAINTENANCE WORKS AT THE FLEXICOKER UNIT DURING SHUT DOWN OF MARCH 2014 IN THE ELEFSINA INDUSTRIAL COMPLEX

 
<< Previous  |   Next >>

Cookies are small text files that are stored in our browser while browsing the web. Their purpose is to notify the site that the user visits for his previous activity. They typically describe our username and password when we visit the same site later, remember us and do not need to login.
 

Learn More ...

These are the cookies used by our website to improve your browsing and temporarily store your preferences.

Disabling them is likely to cause problems in viewing the site .

You can set your browser to block or alert you to these cookies, but some parts of the site will not work properly.